NFR Construction GM Conducts Inspection of Key Sections of Jiribam – Imphal New Line Project
Guwahati, 24th August, 2026:
Northeast Frontier Railway (Construction) General
Manager Shri Ashish Bansal recently conducted inspection of the Jiribam – Khongsang,
Khongsang – Awangkhul and Awangkhul – Imphal sections under the prestigious
Jiribam – Imphal New Line Railway Project. During the inspection, he reviewed
the progress of various ongoing construction activities and assessed the status
of important railway infrastructure works along the project alignment. Shri
Ashish Bansal also inspected the Khongsang–Awangkhul section, including the
yards, with particular focus on preparedness for the CRS inspection planned in
October 2026. He further inspected Tunnel Nos. 28 and 12 and reviewed the
progress of tunnelling works in the project.
The Jiribam –
Imphal New Line Project has a total length of 110.625 km and is one of the most
challenging railway infrastructure projects being undertaken in the Northeast.
The project traverses difficult and hilly terrain and involves extensive
tunnelling and bridge construction. The new railway line is being developed to
provide direct rail connectivity to Imphal,
the capital of Manipur, thereby strengthening the
transportation network of the state and the region.
A major feature of the project is its extensive tunnel
network. The project comprises 54
tunnels with a cumulative length of approximately 66.47 km. The
construction of these tunnels through challenging geological and mountainous
terrain represents a significant engineering achievement and requires advanced
construction techniques along with stringent safety and quality measures.
The project also includes 15 major bridges and 116 minor bridges,
including the tallest bridge no. 164 at Noney with pier height of 141 meters.
These structures are being constructed to facilitate safe and uninterrupted
movement of trains as well as road traffic across the railway alignment.
There are total of 11 railway stations on the Jiribam – Imphal New Line.
The stations are Jiribam,
Vangaichungpao, Rani Gaidinliu, Kambiron Halt, Thingou, Khongsang, Awangkhul,
Noney, Tupul, Haochong Road Halt and Imphal. These stations
will provide improved rail access to the people residing in the surrounding
areas and will serve as important points for passenger and goods movement.
The project is being executed in phases. The Jiribam – Vangaichungpao section, was commissioned
in February 2017, while the Vangaichungpao – Khongsang section, was commissioned in September 2022.
The remaining sections are being progressed in a phased manner towards
completion.
During the inspection, Shri Ashish Bansal emphasized
the need to maintain the highest standards of safety, construction quality and timely execution. He
reviewed the progress of works with the concerned officials and field personnel
and directed them to closely monitor construction activities and resolve issues
promptly to ensure smooth progress of the project.
The Jiribam – Imphal New Line will significantly
improve connectivity between Manipur
and the rest of the country. Besides providing faster and more
reliable passenger transportation, the railway line will facilitate the
movement of essential commodities and goods, significantly augment
transportation and contribute to the overall economic and social development of
the region.
The inspection reflects the continued commitment of Northeast Frontier Railway (Construction) towards
the expeditious completion of major railway infrastructure projects in the
Northeast with a strong focus on safety,
quality and efficient execution.